Steps to be Followed for Shut Down
Q. State the steps to be followed for shut down.
Following Procedure is Followed for Obtaining Permits for Shut down
For major, routine repairs and emergency work on the electric lines (Transmission line, feeder line on distributor line) maintenance programm is prepared and declared. For this major work long period is required and hence a notice is to be published in the news papers to know the shut down periods by the HT / LT consumers. Who receive power / domestic supply from the lines.
The in charge of such work applies to the higher authorities to get the permission of sun down for this work. The permission is to be taken applying in the standard proforma which are of the following types.
Permits for Shut down :
(A) Form for obtaining ‘shunt – down’ of Electric supply :
From : ______________________________________________
[Name and designation of receiving person]
To : ________________________________________________
[Name of the authorized person permitting the work]
Please arrange to cut off electric supply to the lines and issue me ‘Permit to work’ as per rule
- Shut down period from date / time ___________ to __________ (date and time)
- Line’section for which permit is required ____________________________
- Details of work to be carried out for which shut down is required ____________Station
Date / Time
Signature
Designation (stamp)